Bagram Bulk Fuel Storage and Supply Phase 5 & 8, Bagram Air Base
The brief summary of the project:
The Project was carried out at Bagram Air Base in order perform as a fuel storage and supply facility. Storage tank with pump facility, filter building with controls, fill & issue lines, fill stands, POL pipeline underground works were within the scope of the project.
Project Details
Project Type | Bid – Build |
Project Location | Bagram, AFGHANISTAN |
Owner | USACE |
Project Start | 18 June 2009 |
Project End | 23 June 2011 |
Contract Value | $ 24,323,632.00 |
The scope of the project:
Three (3) 25,000 Barrel TS‐1 Storage Tank with Pump Facility; cut and cover tank with concrete pump house built on top of each tank and associated materials/equipment to connect into the under construction South Tank Farm Facility. Metal Plates are butt welded to construct fuel storage tank’s bottom, shield and upper respectively. Tank is coated and tested according to contract specifications. End of the pump house building; pumps, pipes and control equipments are installed and tested properly.
Filter Building with Controls, Fill & Issue Lines: Poured in place concrete facility with CMU panels which houses the filter separators and automatic system controls, generator room and toilet. Filter separators are mounted on base in compliance with contract specifications. Pipe and equipments shall be installed and control valves shall be integrated and tested.
Three (3) new fill stands. Refueler fill stands are connected to pipe loop supply. Control equipments are installed and arranged according to the specifications.