The intent is to make the repairs in phases while maintaining airfield operations. In order for repairs to be made on the Primary Landing Surface, the Old Runway will need to be repaired for temporary service.
The Period of Performance is 330 days and it is scheduled to be turned over to the client before winter. Therefore Serka has taken all the precautens in order not to encounter any problems which may cause delay to the project. Serka was moblized in a timely manner. 120t/hr Asphalt plant was set up in the Bagram Air Field, being the one of the only two Asphalt Production Facility in the Base.
Phase 1 Asphalt works has started on the proposed date and completed İn August. Phase 2 has already started and site process is ahead of the proposed baseline schedule. The project includes the demolition of existing 90,000 sqm concrete and 70,000 sqm asphalt area. Total of 140,000 sqm asphalt will be placed (90,000 sqm has already been completed for Phase 1). Plane Catching System will also be installed for Primary Landing Surface.
Key Project Quantities: