Key Project Quantities:
-
- 15 x Nordex N117/3000 kW
- 15 x 3 MW = 45 MWm/44 MWe
- 62,5/50 MVA Transformer Substation
- Production : 170.800.000 kWh ( P50 )
- Capacity factor : %44
- 13 km access roads
- 36 km underground MV cable
- 25 km F/O cable
Project Type | Design – Build |
Project Location | Tekirdağ, TURKEY |
Owner | Beşiktepe Enerji Üretim ve Ticaret A.Ş. |
Project Start | 1 September 2014 |
Project End | 1 November 2015 |
Contract Value | $ 62,000,000.00 |